Hanoi's new Gia Binh airport tentatively set to open 31 May 2027
Gia Binh International Airport, the planned new hub for Hanoi and the Capital Region in Bac Ninh province, is tentatively due to open on 31 May 2027, starting with a VIP terminal. The commercial passenger terminal will follow in a later phase, with no date given.

Gia Binh International Airport, the planned new international hub for Hanoi and the Capital Region, is tentatively scheduled to open on 31 May 2027, initially with a VIP terminal only. The airport, in Bac Ninh province, is being developed by Masterise Aviation Infrastructure JSC (MAI), part of Masterise Group. The commercial passenger terminal is a separate later phase, and no opening date has been announced for it.
Key facts
- Tentative opening: 31 May 2027, starting with the VIP terminal
- Location: Bac Ninh province, Hanoi Capital Region; IATA code GBN, ICAO code VVGB
- Investment: about VND 196.3 trillion (around US$7.5 billion) on a site of about 1,885 hectares
- Planned capacity: 30 million passengers a year by 2030, rising to 50 million by 2050
- Road link: a direct expressway to Hanoi is due to open at the end of October 2027, with a journey time of about 25 minutes
What is the new airport?
Gia Binh International Airport (GBIA) is described as the new international airport for Hanoi and the Capital Region. Vietnam's Ministry of Public Security is the project owner and selected Masterise as investor in August 2025, with ground broken the same month.
Vietnam's National Assembly approved the scheme in December 2025 under Resolution 256/2025/QH15. MAI is the investor and developer and is building the organisation that will run the airport.
When do the new airport's facilities open?
MAI gives the key dates as tentative. The airport is due to officially open on 31 May 2027, beginning with a VIP terminal and fixed-base operator (FBO) for private aviation, both run by MAI. The direct expressway to Hanoi follows at the end of October 2027. The commercial passenger terminal is planned as a separate phase, but no date has been given.
How big will the airport be?
The airport is designed for 30 million passengers and 1.6 million tonnes of cargo a year by 2030, rising to 50 million passengers and 2.5 million tonnes by 2050. It will have two runways, able to handle 70–80 movements an hour at full development.
GBIA is designed to Skytrax five-star standards, with architecture inspired by the Vietnamese "Heaven, Earth and Humanity" philosophy. Plans also include an aerotropolis: an airport city, free trade zone, and logistics and industrial parks around the site.
How will travellers reach Hanoi?
A direct expressway to Hanoi is due to open at the end of October 2027, which MAI says will bring the journey to about 25 minutes. No other transport links are described in the project information.
Who is behind the project?
MAI's leadership includes Chief Executive Officer Vu Hoang Long and Deputy Chief Executive Officer Denis Bugrov. daa International, the international arm of the Dublin Airport Authority group, signed a technical services contract with MAI in May 2026. Design and planning partners listed include SOM, NACO, Nikken Sekkei, Artelia and AAC, with McKinsey & Company also supporting the project.
What this means for travellers
Gia Binh airport is not yet open, so flights to and from Hanoi are unaffected for now. Because the first phase is a VIP terminal rather than a commercial passenger terminal, travellers should check which airport their flight uses once schedules for the new hub are published, and note that the opening dates given so far are tentative.
MAI says its commercial teams are working with airlines, airports, tourism boards and logistics partners on route launches and marketing. The commercial passenger terminal remains the phase to watch, with no opening date announced yet.