Tonga Airport Upgrade to Bring Bigger Terminal, More Counters by March 2028

Japan is funding a 2.5 billion Yen ($38 million Tongan Pa'anga) upgrade of Fua'amotu International Airport, with works due to be complete by the end of March 2028. Travellers can expect a larger terminal, more arrival counters and a new boarding bridge.

Tonga Airport Upgrade to Bring Bigger Terminal, More Counters by March 2028
Illustrative image

Tonga's Fua'amotu International Airport is set for a major rebuild funded by a grant from the Government and people of Japan worth 2.5 billion Japanese Yen, or $38 million Tongan Pa'anga. The project was launched at a groundbreaking ceremony on 24 November 2026, led by HSH Prince Tungi, and works are scheduled to be complete by the end of March 2028.

Key facts

  • Funding: 2.5 billion Japanese Yen / $38 million Tongan Pa'anga grant from Japan
  • Groundbreaking: 24 November 2026, led by HSH Prince Tungi
  • Completion: scheduled for the end of March 2028
  • Location: Fua'amotu International Airport, Tongatapu, Tonga
  • Contractor: Kitano Construction Corporation; consultants ADAMIS Ltd and Oriental Consultants Global Co.
  • Current traffic: almost 178,000 international passengers and more than 1,900 international flights a year

What is changing at the airport?

The project covers six major upgrades at the international terminal. The departure lounge, check-in area and departure passport control area will all be expanded, and a new passenger boarding bridge will be installed, linked to the terminal by elevated passenger corridors and lifts.

A shelter will be added over the terminal area to protect drop-off points, passengers and other airport users from rain. In the arrivals area, the number of passenger control counters will be increased to help reduce congestion, and a new health room will be provided for travellers with health issues.

The aircraft parking apron will be expanded to hold two large jet aircraft such as Boeing 787s and one smaller jet such as an Airbus 321. Corroded steel columns at the terminal will also be repaired. The existing international terminal was built in 1989 with grant assistance from the Government of Japan.

Why is the work being done?

Chief Executive of Tonga Airports Limited (TAL), Mr. Poasi Tei, said growing passenger numbers, increased traffic and ageing facilities had created challenges in providing efficient and comfortable services. The aim, he said, is a safer, more comfortable and more efficient airport for passengers, airlines and other users.

Mr. Tei noted that international passenger traffic is projected to grow to more than a quarter of a million by 2032. By 2030, passenger numbers are expected to rise by almost 40%, with international flights increasing by almost 25%. Prime Minister Lord Fakafanua said a growing visitor economy strengthens local businesses, supports employment and creates lasting benefits across the Kingdom.

What this means for travellers

Passengers using Fua'amotu International Airport can expect a larger departure lounge, check-in and passport control areas, more arrival control counters and a covered drop-off area once the works are complete. The project is scheduled to be finished by the end of March 2028; the source does not state whether any parts of the terminal will be affected or restricted during construction, so travellers should check current airport arrangements before flying.

Japan's Ambassador to Tonga, HE Inagaki Hisao, described the project as "an additional symbol of our enduring friendship" between the two countries. The groundbreaking ceremony was attended by members of the diplomatic corps and senior government officials.

Construction is being carried out by Japanese company Kitano Construction Corporation, with the consultant team from the preparatory survey including ADAMIS Ltd and Oriental Consultants Global Co. No further milestones have been announced beyond the end-of-March 2028 completion target.